The Establishment of an Agricultural Park in Kwu Tung South (Phase 1)

Project Number:

7473RO
Attachment 1

Brief Description of Project Scope:

The scope of the project comprises:

a. formation works for about 7.5 hectares (ha) of land;

b. related infrastructures including drainage, sewerage, irrigation, water supply, utilities and street lighting; 

c. associated park facilities including basic lodging and storage units; and 

d. construction of about 900 metres (m) long access road and footpaths (including a culvert bridge of about 5m wide; and two vehicular bridges with associated footpaths of about 20m and 40m long respectively) connecting the existing Tsiu Keng Road.

Project Office in Civil Engineering and Development Department:

North Development Office (Enquiry: 3797 5387)

Consultant:

Jacobs China Limited

Approved Project Estimate:

$176.6 million

Current Progress:

Works commenced on 2 October 2020.

Contract:

Contract No. ND/2018/02

Scope: Same as project scope above.
Commencement Date: 2 October 2020
Completion Date: 2024
Contract Sum: About $120 million
Contractor: Harvest - Tsun Yip Joint Venture

Other Related Information:

Scheme / Authorization of Scheme
Gazette Date Subject

21 DEC 2018 &
28 DEC 2018

Authorization of Scheme

3 NOV 2017 &
10 NOV 2017

Scheme