Integrated Basement for West Kowloon Cultural District – remaining works
Project Number:
7763CLBrief Description of Project Scope:
The scope of works comprises –
(a) detailed design and site investigation of essential basement structure 2 and associated works for Zone 2BC of Integrated Basement ("IB"), including preparation of tender documents and assessment of tenders for the construction works;
(b) construction of the foundation works for IB in Zones 2A and 2BC ("IBZ2);
(c) construction of essential basement structure and associated works for IBZ2;
(d) construction of an underground road of about 800 metres long in IBZ2, and associated works including footpaths, pick-up/drop-off area, water supply, drainage, electrical and mechanical ("E&M") works, fire services installation works, plant rooms, and means of escape/means of access for firefighting and rescue; and
(e) necessary environmental mitigation measures, as well as related monitoring and auditing works.
Project Office in Civil Engineering and Development Department:
South Development Office (Enquiry: 3842 7062)Approved Project Estimate:
$17,472.3 millionStatus:
Under constructionCurrent Progress:
The first major works contract commenced on 8 May 2020.