Site Formation and Infrastructure Works for Public Housing Developments at Pik Wan Road, Yau Tong

Project Number:

B812CL
Attachment 1

Brief Description of Project Scope:

  1. site formation works and construction of associated retaining structures and slopes;
  2. construction of pedestrian walkway systems including footpath and two footbridges;
  3. road widening works at Ko Chiu Road and Ko Chiu Path;
  4. road improvement works at Pik Wan Road, Lei Yue Mun Road and junctions of (i) Pik Wan Road and O King Road, (ii) Pik Wan Road and Ko Chiu
    Road, and (iii) Cha Kwo Ling Road and Ko Chiu Road; and
  5. ancillary works including drainage, sewerage, water supply and landscaping.

Project Office in Civil Engineering and Development Department:

Civil Engineering Office / Special Duties (Works)

Consultant:

WSP (Asia) Limited

Current Progress:

Construction works commenced in December 2020.

Contract:

Contract no. CV/2019/03

Contract Title: Site Formation and Infrastructure Works at Pik Wan Road, Yau Tong

Commencement Date: 7 December 2020

Contract Sum: HK$600 million

Contractor: China Road and Bridge Corporation

Contract no. CV/2023/03

Contract Title: Lift and Pedestrian Walkway System between Pik Wan Road and Lei Yue Mun Road, Yau Tong

Commencement Date: 25 January 2024

Contract Sum: HK$395 million

Contractor: CW - KL JV

Other Related Information:

Gazette Date Subject
30 Jan 2019

Authorization of Scheme

9 Nov 2018 & 16 Nov 2018

Scheme