Construction of Subway in support of the Provision of Columbarium at On Hing Lane, Shek Mun, Sha Tin

Project Number:

5193TB
Attachment 1

Brief Description of Project Scope:

(a) construction of a subway of about 50 metres long with eight metres internal width underneath and
across Tate's Cairn Highway connecting On Muk Street and the columbarium;

(b) provision of footpaths at both ends of the subway with suitable queuing areas;

(c) provision of lighting, drainage and other necessary services for the subway; and

(d) provision of barrier-free access, landscaping works and ancillary facilities.

Project Office in Civil Engineering and Development Department:

Civil Engineering Office / Land Works Division

Consultant:

WSP (Asia) Limited

Current Progress:

Construction commenced on 20 January 2021.

Contract:

Contract No.  CV/2020/02
Scope Same as project scope
Contract Sum $149.15 million

Contractor:

Wing Tat Civil Engineering Co. Limited

Other Related Information:

Scheme  / Authorization of Scheme
Gazette Date Subject

22 FEBRUARY 2019 &
1 MARCH 2019

Authorization of Scheme

9 NOVEMBER 2018 &
16 NOVEMBER 2018

Scheme

Back