Kai Tak development - remaining infrastructure works for developments at the former runway and south apron
Project Number:
7833CLBrief Description of Project Scope:
The scope of the project comprises:
(a) a single two-lane Road L10 (Northern Section) of about 370m Long
(b) extension and improvement of Kai Hing Road with the associated improvement of Lam Chak Street
Project Office in Civil Engineering and Development Department:
East Development Office (Enquiry: 3842 7173)Consultant:
Hyder-Meinhardt Joint VentureApproved Project Estimate:
135.2 millionCurrent Progress:
The works commenced on 30 June 2020. The delivery of Stage 5 works is on schedule.
Contract:
Contract No. ED/2018/04
Contractor:
Bouygues Travaux Publics