Site formation and infrastructure works for public housing developments at Long Bin, Yuen Long

Project Number:

B810CL

Brief Description of Project Scope:

The scope of the project mainly comprises:

(a) Site formation works;

(b) A single two-lane carriageway with footpaths connecting Ma Fung Ling Road to Long Tin Road;

(c) A footbridge over Castle Peak Road – Ping Shan and associated lift towers;

(d) A footbridge over Long Tin Road and associated lift towers;

(e) A footbridge over Yuen Long West Nullah;

(f) A public transport interchange; and

(g) Ancillary works including drainage, sewerage, waterworks and landscaping works.

Project Office in Civil Engineering and Development Department:

Civil Engineering Office / Housing Projects 2 Division

Consultant:

Ove Arup and Partners Hong Kong Limited

Current Progress:

Construction commenced in October 2021.

Contract:

Contract no. CV/2021/05

Contract Title: Infrastructure Works for Public Housing Developments at Long Bin, Yuen Long - Castle Peak Road (Ping Shan) and Long Tin Road

Commencement Date: 30 October 2021

Contract Sum: $322 million

Contractor: CNCEC - CRCC15 Joint Venture



Contract no. CV/2022/07

Contract Title: Site Formation and Infrastructure Works at Long Bin, Yuen Long – Phase 2

Commencement Date: 3 October 2022

Contract Sum: $594 million

Contractor: Build King - Richwell Engineering Joint Venture

Other Related Information:

Gazette Date Subject
22 January 2021

Authorization of Scheme

20 December 2019

Scheme

20 December 2019

Scheme