B858CLBrief Description of Project Scope:
The scope of the project comprises:-
- site formation works at Sites 1, 4a-1 and 6 and construction of associated retaining structures and slopes;
- construction of a single two-lane carriageway with footpaths connecting to Tung Wui Road at Site 1;
- widening of a section of Kam Po Road from an existing single-lane road to a single two-lane carriageway with footpaths and a cycle track;
- improvement works at the junction of Tung Wui Road and Kam Po Road;
- construction of a lay-by and road improvement works at Kam Ho Road;
- road improvement works at Tung Wui Road, and provision of a cycle parking area near Site 6; and
- ancillary works including drainage, sewerage, water supply and landscaping works.
Project Office in Civil Engineering and Development Department:
West Development Office (Enquiry: 2158 5680)Consultant:
AECOM Asia Company LimitedApproved Project Estimate:
$907 millionCurrent Progress:
Works commenced in June 2021.
Contract:
Contract No. YL/2020/04
Scope: | Same as project scope above |
---|---|
Commencement Date: | 28 June 2021 |
Completion Date: | 2026 |
Contract Sum: | $475 million |
Contractor: | Sang Hing – Kuly Joint Venture |