Site formation and infrastructure works for public housing developments at Pok Fu Lam South

Project Number:

795CL
Attachment 1

Brief Description of Project Scope:

The scope of works comprises –

  1. site formation works and construction of associated retaining structures and slopes;
  2. construction of a single two-lane carriageway, footpaths and lay-bys, including an elevated road, for connecting the Kai Lung Wan North Site with the junction of Pok Fu Lam Road and Victoria Road;
  3. road improvement works at the junction of Pok Fu Lam Road and Victoria Road, and road widening works for a section of Victoria Road connecting to the junction;
  4. construction/ modification of lay-bys and footpath widening works including the construction of covered footpath at Shek Pai Wan Road;
  5. construction of two footbridges with associated lifts across Shek Pai Wan Road;
  6. road improvement works at Wah Lok Path, Wah King Street, Wah Fu Road and near World Fair Court; and
  7. ancillary works including drainage, sewerage, water supply and landscaping.

Project Office in Civil Engineering and Development Department:

Housing Projects 3 Division, Civil Engineering Office

Consultant:

Ove Arup & Partners Hong Kong Ltd

Current Progress:

The works for the project of Site Formation and Infrastructure Works for the Public Housing Developments at Pok Fu Lam South were commenced on 22 December 2020.

Contract:

Contract No. CV/2020/01
Scope: The works mainly include site formation works of land platform with a total area of about 7 ha, construction of two footbridges and an access road, road widening/ junction improvement and ancillary works including drainage, sewerage, waterworks and landscaping works.
Commencement Date: 22 December 2020
Completion Date: End 2026
Contract Sum: HK$2,542.238 million

Contractor:

China Harbour - China Geo Joint Venture

Other Related Information:

Gazette Date Subject
25 Oct 2019 & 1 Nov 2019

Authorization of Scheme

21 Sep 2018 & 28 Sep 2018

Scheme

15 Jan 2021