Site Formation and Infrastructure Works for Public Housing Developments at Cheung Muk Tau
Project Number:
B807CL
Brief Description of Project Scope:
The scope of works comprises –
- site formation works for about 2.84 hectares of land and construction of associated retaining walls and slopes;
- construction of a carriageway with a length of about 500 metres, footpaths, cycle track, lay-bys and associated retaining walls, connecting Nin Fung Road;
- road improvement works at Nin Fung Road with a length of about 500 metres;
- road improvement works at the roundabout at the junction of Sai Sha Road/Nin Fung Road/Nin Wah Road and at the junction of Sai Sha Road and Kam Ying Road; and
- ancillary works including drainage, sewerage, waterworks and landscaping works.
Project Office in Civil Engineering and Development Department:
Housing Projects 1 Unit, Civil Engineering Office
Approved Project Estimate:
$511.1 Million
Current Progress:
Construction works commenced in September 2023.Contract:
Contract No.: |
CV/2023/09 |
Contract Title: |
Site Formation and Infrastructure Works at Cheung Muk Tau |
Scope: |
Same as project scope |
Commencement Date: |
September 2023 |
Contract Sum: |
$410 Million |
Contractor:
Lanon Development Limited