Site Formation and Infrastructure Works for Public Housing Development at Area 48, Fanling
Project Number:
B784CLBrief Description of Project Scope:
The scope of the project mainly comprises:(a) site formation works and construction of associated retaining walls and slopes;
(b) construction of a carriageway, lay-bys and footpath connecting to the proposed re-aligned Tai Wo Service Road West; and
(c) ancillary works including drainage, sewerage, waterworks, land decontamination and landscaping works.
Project Office in Civil Engineering and Development Department:
Project Unit, Civil Engineering OfficeConsultant:
Ove Arup & Partners Hong Kong LimitedApproved Project Estimate:
$1,145 millionCurrent Progress:
Construction commenced in January 2023.Contract:
Contract No. CV/2022/08
Site Formation and Infrastructure Works at Area 48, Fanling
Scope: |
Same as project scope above |
Commencement Date: |
January 2023 |
Contract Sum: |
$718 million |
Contractor: |
Paul Y. - Tsun Yip Joint Venture (CV202208) |