Site Formation and Infrastructure Works for Public Housing Developments at Tuen Mun Central - Phase 2

Project Number:

B811CL
Attachment 1

Brief Description of Project Scope:

(a) formation of about 3.3 hectares of land for the proposed public housing development at Tuen Hing Road ;

(b) construction of a carriageway with associated footpaths connecting the Tuen Hing Road Site and Tuen Hing Road; and

(c) ancillary works including drainage, sewerage, water supply, slope stabilisation and landscaping.

Project Office in Civil Engineering and Development Department:

Housing Projects 2 Division, CEO

Consultant:

Binnies Hong Kong Limited

Approved Project Estimate:

$599.0M

Current Progress:

Construction works commenced in July 2023.

Contractor:

Contract No. CV/2023/04

Scope:

The works mainly comprise site formation works, slope works, construction of a carriageway and footpath connecting to existing Tuen Hing Road, and the ancillary works including drainage, sewerage, waterworks and landscaping works.

Commencement Date:

31 July 2023

Contract Sum:

$440M

Contractor:

China Civil Engineering Construction Corporation

Other Related Information:

Gazette under Roads (Works, Use and Compensation) Ordinance (Chapter 370)

Gazette Date Subject

17 FEB 2023 & 24 FEB 2023

Authorization of Phase 2 Road Works

24 DEC 2021 & 31 DEC 2021

Scheme of Phase 2 Road Works