San Tin Technopole Phase 1 Stage 1 Works - Site Formation and Engineering Infrastructure

Project Number:

7899CL
Attachment 1

Brief Description of Project Scope:

  1. site clearance and formation (including geotechnical works and land decontamination works) for about 158 hectares ("ha") of land, to supply land for development of innovation and technology ("I&T") uses, logistics, housing, Government, Institute or Community ("GIC") facilities, open spaces, etc., and for construction of the road and infrastructure works in sub-paragraphs (b) and (c) below;
  2. upgrading of a section of San Tin Highway of about 2 kilometres ("km"), construction of associated district distributors and local roads of about 8 km long in total, cycle tracks of about 8.5 km long and footpaths, and associated junction/road improvements;
  3. construction of other engineering infrastructure works including drainage system, sewerage system (including two sewage pumping stations); water supply systems (including a fresh water service reservoir and a reclaimed water service reservoir with capacity of about 132 000 cubic metres ("m3 ") and 72 000 m3 respectively); revitalisation of drainage channels of around 2 400 metres ("m") long, greening and landscape works for open space and amenity area, as well as other associated works;
  4. implementation of the environmental mitigation measures, environmental monitoring and audit ("EM&A") programme and construction supervision for the works mentioned in sub-paragraphs (a) to (c) above; and
  5. detailed design for the expansion in development area (belonging to the works after Phase 1 Stage 1) after the Northern Metropolis Development Strategy was announced.

Project Office in Civil Engineering and Development Department:

North Development Office (Enquiry: 3547 1624)

Consultant:

AECOM - Halcrow Joint Venture
Arup - Binnies Joint Venture

Approved Project Estimate:

$27.1751 Billion

Related Website:

https://nm-santintech.hk/en/

Current Progress:

Construction commenced in December 2024

Contract:

Contract no. ND/2024/09

Scope:

The works mainly comprise:

  1. site formation of lands (including site clearance) and ground investigation works;
  2. land decontamination works;
  3. archaeological survey;
  4. diversion works of existing roads, cycle tracks, drainage, sewerage, water supply and utilities systems; and
  5. implementation of environmental mitigation measures and environmental monitoring works for the works mentioned above.

Commencement Date:

31 December 2024

Completion Date:

2027

Contract Sum:

$359.23 Millions

Contractor:

CR15G-Tung Lee Joint Venture

Contract no. ND/2024/10

Scope:

The works mainly comprise:

  1. site formation of lands (including site clearance) and ground investigation works;
  2. construction of at-grade Road L27 connecting to Lok Ma Chau Road;
  3. construction of associated works including footpaths, drainage (including construction of box culverts), sewerage, water mains, landscaping works and slope works; and
  4. implementation of environmental mitigation measures and environmental monitoring works for the works mentioned above.
Commencement Date: 31 December 2024

Completion Date:

2028

Contract Sum:

$228.64 Millions

Contractor:

Kuly Construction & Engineering Company Limited

Other Related Information:

https://nm-santintech.hk/en/information-centre/dl/