Advance Site Formation and Engineering Infrastructure Works at Kwu Tung North and Fanling North New Development Areas
Project Number:
7747CLBrief Description of Project Scope:
The project is part of the first phase of the Kwu Tung North (KTN) and Fanling North (FLN) New Development Area (NDA) development and comprises mainly:
- site formation of about 70 hectares ("ha") of land (including soil treatment works) in the KTN and FLN NDA;
- construction of the Fanling Bypass (Eastern Section) of about 4 kilometres ("km") long, which is a dual two‐lane carriageway connecting the FLN NDA to Fanling Highway, about 10 km of local roads and about 10 km of footpaths, and about 4 km cycle tracks within the NDA area, and associated junction/road improvements;
- engineering infrastructure works including drainage, sewerage (including two sewage pumping stations), waterworks (including a fresh water service reservoir of about 27 500 cubic metres ("m3") capacity and a flushing water service reservoir of about 11 500 m3 capacity in the KTN NDA), landscaping works and slopeworks;
- part expansion and upgrading of Shek Wu Hui Sewage Treatment Works ("SWHSTW") to increase its treatment capacity by 20 000 m3 per day;
- reprovisioning works; and
- implementation of environmental mitigation measures and environmental monitoring and audit ("EM&A") programme for the works mentioned in paragraphs (a) to (e) above.
Project Office in Civil Engineering and Development Department:
North Development Office (Enquiry: 3547 1615)Consultant:
AECOM Asia Company LimitedApproved Project Estimate:
$17.32 BillionRelated Website:
http://ktnfln-ndas.gov.hk/en/index.php
Current Progress:
Construction commenced in September 2019
Contract:
Contract no. ND/2019/06
Scope: |
The contract mainly comprises construction of an in-situ reprovisioned NDTWM and its facilities involving a steel canopy for the trading area and a management office building. |
Commencement Date: |
27 September 2019 |
Completion Date: |
17 March 2022 (Actual Completion) |
Contract Sum: |
$232 Millions |
Contractor: |
New Concepts Engineering Development Limited |
Contract No. ND/2019/01
Scope: |
The works mainly comprise site formation of land under the First Phase of KTN NDA (including soil treatment works); construction of engineering infrastructures including drainage works, sewerage works (including temporary sewage treatment facilities), waterworks (including a fresh water service reservoir and a flushing water service reservoir), roadworks (including carriageway, footpaths, cycle tracks, a subway and junction improvement), pipeworks for district cooling system, slope works and landscaping works; and construction of associated environmental mitigation works including noise barriers/noise enclosures and low noise road surfacing. |
Commencement Date: | 6 December 2019 |
Completion Date: | End 2026 |
Contract Sum: | $2.578 Billions |
Contractor: | Build King - Richwell Engineering Joint Venture |
Enquiry: | 5975 8579 |
Contract No. ND/2019/02
Scope: | The contract mainly comprises road and drainage works between Kwu Tung North New Development Area and Shek Wu Hui; construction of a sewage pumping station, a Long Valley Nature Centre and a footbridge spanning across Sheung Yue River; and site formation of land and the associated engineering infrastructure works for a village resite area in Kwu Tung North New Development Area. |
Commencement Date:
|
17 February 2020 |
Completion Date:
|
2025 |
Contract Sum:
|
$598 Millions |
Contractor:
|
Chun Wo - Kwan Lee Joint Venture
|
Enquiry:
|
6846 0156 |
Contract No. ND/2019/05
Scope: |
The contract mainly comprises construction of an approximately 2 kilometres (km) long dual two-lane Fanling Bypass Eastern Section between Shung Him Tong and Kau Lung Hang mainly on viaducts with two long span overbridges across the existing East Rail Line; realignment of part of the existing Tai Wo Service Road East, Tai Wo Service Road West and Fanling Highway; construction of approximately 2.4 km long noise barriers, and relocation of approximately 400 metres long existing noise barriers along Fanling Highway; alteration and addition works to the existing Ho Ka Yuen footbridge; reprovisioning of a bus-bus interchange at Fanling Highway with a proposed public toilet and covered walkway; and associated slope works, ground investigation, geotechnical instrumentation and monitoring, retaining wall, drainage works, waterworks, sewerage works, traffic control and surveillance system installation, electrical and mechanical works and landscaping works. |
Commencement Date: | 2 March 2020 |
Completion Date: | 2025 |
Contract Sum: | $2.268 Billions |
Contractor: | CRCC – Paul Y. Joint Venture |
Enquiry: | 9737 1021 |
Contract No. ND/2019/07
Scope: |
The works mainly comprise site formation of land under the First Phase of Fanling North New Development Area; and construction of engineering infrastructures including drainage and sewerage works, waterworks, roadworks (including carriageway, footpaths and cycle tracks), noise barrier works, slope works and landscaping works. |
Commencement Date: |
31 August 2020 |
Completion Date: |
2024 |
Contract Sum: |
$315 Millions |
Contractor: |
China Road and Bridge Corporation |
Enquiry: |
5925 7173 |
Contract No. ND/2019/04
Scope: | The contract mainly comprises construction of an approximately 2-kilometre-long dual two-lane Fanling Bypass Eastern Section between Shek Wu San Tsuen North and Lung Yeuk Tau comprising viaduct, at-grade road and underpass sections; construction of Lung Yeuk Tau Interchange connecting Fanling Bypass Eastern Section with existing Sha Tau Kok Road – Lung Yeuk Tau; construction of a footbridge across Ng Tung River and a cycle track cum footbridge over Lung Yeuk Tau Interchange; construction of a sewage pumping station adjacent to Lung Yeuk Tau Interchange; reprovisioning of the On Lok Mun Street Playground, public toilet and refuse collection point near Lung Yeuk Tau Interchange; road junction improvement works in the North District; and associated ground investigation, geotechnical instrumentation and monitoring, slope and retaining wall works, drainage and sewerage works, waterworks, noise barrier works, traffic control and surveillance system installation, electrical and mechanical works and landscaping works. |
Commencement Date: | 14 August 2020 |
Completion Date: | 2025 |
Contract Sum: | $2.148 Billions |
Contractor: | DCK JV (Daewoo - Chun Wo - Kwan Lee Joint Venture) |
Enquiry: | 5197 5733 |