First Stage of Site Formation and Engineering Infrastructure at Kwu Tung North and Fanling North New Development Areas
Project Number:
7759CLBrief Description of Project Scope:
The Project is part of the first phase of the Kwu Tung North (KTN) and Fanling North (FLN) New Development Area (NDA) development and comprises mainly :
- development of a nature park at Long Valley of about 37 hectares (ha) including provision of a visitor centre and a footbridge of about 50 metres long spanning across Sheung Yue River for connection between the nature park and the visitor centre;
- reprovisioning of two egretry sites in the FLN NDA and enhancement works to an existing egretry site in the KTN NDA;
- site formation of about 2.3 ha of land (including soil treatment works) for a village resite area and a district police station in the KTN NDA;
- engineering infrastructure works including roads, drainage, sewerage, waterworks, slopeworks and landscaping works; and
- implementation of environmental mitigation measures and environmental monitoring and audit (EM&A) programme for the works mentioned in items (a) to (d) above.
Project Office in Civil Engineering and Development Department:
North Development Office (Enquiry: 3422 3381)Consultant:
AECOM Asia Company LimitedApproved Project Estimate:
$896.4 millionRelated Website:
http://ktnfln-ndas.gov.hk/en/index.php
Current Progress:
Construction commenced in December 2019
Contractor:
Contract No. ND/2019/03
Scope: |
The contract mainly comprises development of a nature park at Long Valley and ecological mitigation and enhancement works for the nature park. |
Commencement Date: | 19 December 2019 |
Completion Date: | Early 2024 |
Contract Sum: | $324 Millions |
Contractor: | Sang Hing - Kuly Joint Venture |
Contract No. ND/2019/02
Scope: | The contract mainly comprises road and drainage works between Kwu Tung North New Development Area and Shek Wu Hui; construction of a sewage pumping station, a Long Valley Nature Centre and a footbridge spanning across Sheung Yue River; and site formation of land and the associated engineering infrastructure works for a village resite area in Kwu Tung North New Development Area. |
Commencement Date:
|
17 February 2020 |
Completion Date:
|
2025 |
Contract Sum:
|
$598 Millions |
Contractor:
|
Chun Wo - Kwan Lee Joint Venture
|