Tseung Kwan O – Lam Tin Tunnel
Project Number:
7823TH
Brief Description of Project Scope:
The project is for the construction of a dual two-lane highway approximately 3.8 km long connecting Tseung Kwan O (TKO) at Po Shun Road in the east with proposed Trunk Road T2 in Kai Tak Development in the west. About 2.2 km of the highway is in the form of tunnel. Tseung Kwan O – Lam Tin Tunnel (TKO-LTT) will meet the TKO external traffic demand as a result of continual development of TKO. TKO-LTT, together with the proposed Trunk Road T2 and Central Kowloon Route, will form the Route 6 which will provide an east-west express link between West Kowloon and TKO areas.
Project Office in Civil Engineering and Development Department:
East Development Office (Enquiry : 3842 7105)
Consultant:
AECOM Asia Co. Ltd.
Approved Project Estimate:
About $15.1 billion
Related Website:
http://www.tko-ltt.hk
Current Progress:
Construction commenced in July 2016
Contract:
Contract No. NE/2015/01
Scope: |
The works include construction of the main tunnel of the TKO-LT Tunnel, construction of tunnel portal facilities and ventilation building at TKO, construction of slip roads, branch tunnels, viaducts, Lam Tin Interchange, tunnel portal facilities, ventilation building and administration building at Kwun Tong, and implementation of the associated building, civil, structural, marine, electrical and mechanical, landscaping and environmental protection and mitigation works. |
Commencement Date: |
11 July 2016 |
Completion Date: |
2022 |
Contract Sum: |
$8.731 billion |
Contractor: |
Leighton-China State Joint Venture |
Contract No. NE/2015/02
Scope: |
The works include reclamation of approximately 3 hectares at Junk Bay, construction of the dual two-lane Road P2 of approximately 800 m long with approximately 200 m of the depressed carriageway covered by landscape deck, and implementation of the associated building, civil, structural, marine, electrical and mechanical, landscaping and environmental protection and mitigation works. |
Commencement Date: |
29 July 2016 |
Completion Date: |
2022 |
Contract Sum: |
$1.777 billion |
Contractor: |
CRBC-Build King Joint Venture |
Contract No. NE/2015/03
Scope: |
The works include construction of a 70m long and 10m wide covered footbridge spanning over Po Shun Road connecting Park Central and Tiu Keng Leng Sports Centre, and ancillary works including a passenger lift, footpath, drainage, retaining walls, landscaping works and electrical & mechanical works. |
Commencement Date: |
16 December 2016 |
Completion Date: |
2019 |
Contract Sum: |
$66 million |
Contractor: |
Wing Lee (SK) Construction Company Limited |
Contract No. NE/2017/01
Scope: |
The works include construction of a marine viaduct forming the TKO Interchange at Junk Bay. |
Commencement Date: |
22 January 2018 |
Completion Date: |
2022 |
Contract Sum: |
$728 million |
Contractor: |
Chun Wo – Shanghai Tunnel – China Metallurgical Joint Venture |
Contract No. NE/2017/02
Scope: |
The works include construction of a section of Road P2 in TKO Town Centre, modification of the existing road junction at Po Yap Road/ Po Shun Road/ Chui Ling Road into a signalised junction, construction of a grade separated footbridge cum cycle track (namely the Southern Footbridge) with provision of lifts, junction improvement at Po Yap Road/ Tong Yin Street. |
Commencement Date: |
30 November 2017 |
Completion Date: |
2022 |
Contract Sum: |
$257 million |
Contractor: |
Zhen Hua Engineering Co., Ltd. |
Contract No. NE/2017/06
Scope: |
The works include design, supply and installation of traffic control and surveillance system and associated works for Tseung Kwan O – Lam Tin Tunnel and Cross Bay Link. |
Commencement Date: |
9 November 2018 |
Completion Date: |
2022 |
Contract Sum: |
$188 million |
Contractor: |
GTECH Services (Hong Kong) Limited |
Other Related Information: