Improvement works at Tai O
Project Number:
7417ROBrief Description of Project Scope:
Phase 1 works include:i. Construction of a riverwall at Yat Chung and the associated drainage and sewerage improvement works;
ii. Upgrading of the temple garden in front of Kwan Tai Temple; and
iii. Improvement to the signage within the inner-core area of Tai O.
Phase 2 Stage 1 works include:
i. Construction of a public open space, a public transport terminus, a public car park for private cars, a loading and unloading area, a cycle parking area and associated roadworks at the western end of Tai O Road;
ii. Provision of on-street parking spaces for coaches and goods vehicles at Lung Shing Street in Yim Tin; and
iii. Landscaping and ancillary works.
Phase 2 Stage 2 works include:
i. Construction of footbridges at Po Chue Tam and Yim Tin;
ii. Upgrading works of the open area in front of Yeung Hau Temple;
iii. Construction of an amphitheatre-cum-open space and a public car park at Yim Tin; and
iv. Ancillary works, including associated road, drainage, water mains, sewerage, utilities, landscaping and public lighting works, etc.
Phase 3 works include:
i. Construction of a promenade and a garden at Shek Tsai Po;
ii. Construction of a footbridge to connect the proposed promenade and the existing Tai O public transport terminus;
iii. Improvement to the existing helipad;
iv. Provision of information and directional signage for inner loop heritage trail and outer loop nature trail;
v. Improvement of existing roads and streetscape within the Tai O inner-core area; and
vi. Other supporting infrastructure including refuse collection point and upgrading/ extension of water reticulation system, etc.
Project Office in Civil Engineering and Development Department:
Sustainable Lantau Office (Enquiry: 2231 4408)Consultant:
Agreement No. CE 27/2009 (CE) – “Improvement Works at Tai O – Design and Construction”- Mannings (Asia) Consultants Limited
Agreement No. CE 12/2017 (CE) – “Improvement Works at Tai O, Phase 2 Stage 2 – Design and Construction”
- Meinhardt Infrastructure and Environment Limited
Agreement No. CE 27/2023 (CE) – “Improvement Works at Tai O, Phase 3 – Design and Construction”
- Meinhardt Infrastructure and Environment Limited
Current Progress:
Phase 1Construction for the works was completed (under PWP Item 7435RO).
Phase 2 Stage 1
Construction for the works was completed (under PWP Item 7469RO).
Phase 2 Stage 2
Construction of the works (under PWP Item 7483RO) commenced in March 2023. The works are expected to be completed in about 3 years.
Phase 3
The works are under detailed design stage.
Contract:
Contract No. IS/2022/01
Scope: |
The contract mainly comprises construction of footbridges at Yim Tin and Po Chue Tam; construction of an amphitheatre-cum-open space and a public car park at Yim Tin; upgrading works of the open area in front of Yeung Hau Temple; and ancillary works, including associated road, drainage, water mains, sewerage, utilities, landscaping and public lighting works, etc. |
Commencement Date: |
31 March 2023 |
Completion Date: |
2026 |
Awarded Sum: |
$286.1 million |
Contractor: |
Tung Lee-CCCC-FHDI Joint Venture |