Kai Tak development – infrastructure for developments at the former runway and south apron

Project Number:

7822CL
Attachment 1Attachment 2Attachment 3

Brief Description of Project Scope:

The scope of Stage 4 comprises:

a.    construction of the following items of works located at the former runway –

      1. a section of dual two-lane Road D3 (Metro Park Section) (MPS) of about 1 130 metres (m) long connecting Shing Kai Road at the former north apron and Road D3A at the former runway, including about 200 m underpass with associated 320 m depressed road, 360 m elevated road and 250 m at grade road;
      2. a single two-lane Road L12d of about 47 m long connecting Road D3A at the former runway;
      3. a salt water pumping station and associated water intake;
      4. a sewage pumping station; and
      5. landscaped decks of about 380 m long in total with a minimum width of about 11 m above Road D3 (MPS) and landscaped area adjoining Road D3 (MPS) providing a total of about 3.9 hectares of public open space.

The scope of Stage 5 comprises:

b.    construction of the following items of works located at the former south apron –

      1. single two-lane roads of about 650 m long in total covering part of Road L10, Road L18 and Road S20; and
      2. a landscaped elevated walkway of about 140 m long, connected with the existing footbridge KF64, with associated lifts and a staircase. 

c.    associated footpaths, street lighting, traffic aids, drainage, sewerage, water mains, landscaping, outfalls, modification of seawall, electrical and mechanical works and ancillary works at the former runway and south apron; and

d.    implementation of environmental mitigation measures and related environmental monitoring and audit (EM&A) works for the works mentioned in items (a) to (c) above.

Project Office in Civil Engineering and Development Department:

East Development Office (Enquiry: 3579 2452)

Consultant:

AECOM Asia Company Limited; Hyder-Meinhardt-Joint Venture.

Approved Project Estimate:

$2.874 billion

Current Progress:

The Stage 4 works commenced on 30 May 2019 and the Stage 5 works commenced on 14 November 2019.

The delivery of both stages of works is on schedule.

Contract:

Contract No. ED/2018/01

Scope:

same as project scope for the Stage 4 above plus other miscellaneous works at the former runway

Commencement Date: 30 May 2019
Completion Date: completion in phases by 2023
Contract Sum: $1.480 billion
Contractor:         Penta-Ocean Construction Co., Ltd.

Contract No. ED/2018/04

Scope:

same as project scope for the Stage 5 infrastructure above plus the project scope of 7785TH (Trunk Road T2 and Cha Kwo Ling Tunnel)

Commencement Date:

14 November 2019

Completion Date:

completion in phases by 2023 (for Stage 5 infrastructure)

Contract Sum:

$10.918 billion (for Stage 5 infrastructure and for Trunk Road T2 and Cha Kwo Ling Tunnel)

Contractor:

Bouygues Travaux Publics

Other Related Information:

Gazette Date Subject

15 March 2019

20 March 2020

25 May 2018 & 1 June 2018

Authorization of Scheme

21 July 2017 & 28 July 2017

Scheme

16 March 2018

Authorization of Scheme

15 December 2017 & 22 December 2017

Scheme

25 May 2018 & 1 June 2018

Authorization of Scheme

15 December 2017 & 22 December 2017

Scheme