West Kowloon Reclamation – main works (remainder) – footbridge at the junction of Sham Mong Road and Hing Wah Street West in Sham Shui Po
Project Number:
7831CLBrief Description of Project Scope:
The scope of the project comprises:
(a) a covered four-span footbridge system at the junction of Sham Mong Road and Hing Wah Street West, with the length of each span ranging from about 45 metres (m) to 58 m (222 m in total) and the clear width of about 4 m;
(b) seven lifts, four covered escalators and two covered staircases linking the proposed footbridge system with the existing and future adjacent developments;
(c) associated road works and ancillary works, including footpaths, drainage, utilities, electrical and mechanical and landscaping works; and
(d) necessary environmental mitigation measures.
Project Office in Civil Engineering and Development Department:
South Development Office (Enquiry: 3842 7062)Consultant:
Mott MacDonald Consultants (Hong Kong) LimitedApproved Project Estimate:
$331.9 millionCurrent Progress:
The works commenced on 23 July 2020 and are on schedule.
Contract:
Contract No. SD/2019/02
Scope: | Same as project scope above. |
---|---|
Commencement Date: | 23 July 2020 |
Completion Date: | Q3 2024 |
Contract Sum: | About $218 million |
Contractor:
Wang Kee Joint Venture