CEDD Signed Contract for Hung Shui Kiu/Ha Tsuen New Development Area Second Phase Development - Contract 4

09/10/2024
The Civil Engineering and Development Department signed a contract of about HK$ 1,710 million on 9 October 2024 with Build King - Tung Lee Joint Venture for carrying out site formation and infrastructure works for Hung Shui Kiu/Ha Tsuen New Development Area Second Phase development.

The works mainly include:-

(1) site clearance and formation (including land decontamination works) for about 43 hectares of lands, together with provision of associated engineering infrastructure;
(2) construction of district distributor and local roads connecting Hung Shui Kiu/Ha Tsuen New Development Area to Tin Ha Road;
(3) construction of pedestrian footbridges;
(4) construction of a cycle track cum pedestrian subway and associated retaining walls;
(5) revitalisation of some sections of Tin Sam Channel;
(6) construction of a sewage pumping station;
(7) construction of associated works including water mains, drainage and sewerage works, district cooling mains, cycle tracks, footpaths, box culverts, landscaping works, electrical and mechanical works and other ancillary works; and
(8) implementation of environmental mitigation measures (including noise barriers) and environmental monitoring works for the works mentioned above.

The works commenced on 27 September 2024 for completion in 2030.